Apex Frame Systems
Public Bid Systems
RFP Breakdown Brief · Sample
Clarify First
Solid civil scope and a fair budget. Confirm your bonding capacity and PennBid prequal status before you spend time on the bid.
Why clarify first

This is a first-read summary of the RFP. Use it to decide whether to pursue and what needs to happen next.

  • Bonding capacity (§ 4.3). 100% performance and payment bonds required at award. If your single-project bond limit is under $5M, get your surety on the phone this week.
  • Prequalification status (§ 3.1). Bidders must be PennBid-registered and either PennDOT-prequalified for water/sewer or hold a current Township vendor approval. Confirm both before you bid.
  • Prevailing wage exposure (§ 7.2). PA Prevailing Wage Act applies. Certified payroll required weekly. Pull your last three PW projects and confirm your process holds up.
  • Coordination with active service (§ 6.4). Existing residents stay on water throughout construction. Temporary bypass and after-hours shutoffs are required. Plan crew and equipment around that.
First-Read Brief

Township of Newton / Water Main Replacement, Phase 2

Owner
Township of Newton, Bucks County, PA
Scope
8,200 LF water main replacement + paving
Bid Due (receipt deadline)
Thu Mar 19, 2:00 PM ET
Engineer's Estimate
$3.8M
Top 3 things that can lose this
  1. Bonding capacity. Per § 4.3, 100% performance and payment bonds are required within 10 days of award. At $3.8M engineer's estimate, that's a real bonding requirement against most small-civil surety lines. Call your surety this week. If they can't sit on $7.6M of aggregate capacity, find a co-surety before you spend time on the bid.
  2. Prevailing wage compliance. Per § 7.2, PA Prevailing Wage Act applies. Weekly certified payroll on PennDOT Form CS-409 or equivalent. Missing or late certified payroll triggers payment withholding under § 8.5. If your last PW project bled hours on payroll prep, build that cost into your fee or don't bid.
  3. Liquidated damages. Per § 9.1, LDs run $1,500 per calendar day past substantial completion (180 calendar days from NTP). $5,000 per day past final completion (30 days after substantial). Build a real schedule with float, not the optimistic one. A 30-day overrun is $45,000 minimum.
Decision check

Bid / No-Bid Scan

Six checks. Start here. Green means go. Yellow means get answers before you spend time on the bid.

!
Bonding capacity?
100% performance + 100% payment bonds at award.
$3.8M each, $7.6M aggregate on this job. If your surety line is under $5M single-project or under $10M aggregate, line up a co-surety before bid day.
!
Prequalification status?
PennBid registration + PennDOT prequal OR Township vendor approval.
Per § 3.1. PennDOT prequal in water/sewer (work code 0530 or 0540) satisfies it. Township vendor approval also satisfies it. Verify your status. Don't assume.
!
Prevailing wage capacity?
PA Prevailing Wage Act applies. Weekly certified payroll required.
Per § 7.2. Wage determination posted in the bid package. If your back-office can't deliver weekly CS-409s on time, either fix that now or don't bid.
!
Insurance thresholds?
GL $2M/$4M, auto $1M, excess $5M, WC statutory.
Per § 4.5. Township named as additional insured with primary/non-contributory wording. Pollution liability $1M/$2M required (per § 4.5.3) because of disturbed soils near former gas station parcel.
!
MBE/WBE participation?
12% MBE + 7% WBE participation goals (combined 19%).
Per § 5.6. Goals, not quotas, but a credible plan is required. Good-faith effort documentation expected. If you're MBE or WBE certified yourself, declare on signature page.
Site access and staging?
Township provides staging area at municipal yard, free of charge.
Per § 6.2. Approximately 0.4 acres, 0.5 miles from the work corridor. Suitable for trench plate, pipe storage, equipment. Saves real money vs. bidding without a yard.
Submission

Submission checklist

Miss any of these and they can throw out your bid unread. Click each box as you confirm it.

0 of 12 done
Schedule

The dates that matter

Six dates between now and award. The receipt deadline in orange is the hard cutoff.

Wed Feb 25
Mandatory pre-bid meeting + site walk. 10:00 AM at Township Municipal Building, then field walk of the corridor. Attendance is mandatory; firms not represented may not bid. § 2.2
Mon Mar 2
Last day to submit written questions via the PennBid Q&A portal. Late questions will not be answered. § 2.3
Fri Mar 6
Final addendum posted on PennBid by 5:00 PM. Check for changes that affect your bid. § 2.3
Thu Mar 192:00 PM ET
Bid receipt deadline. PennBid upload only. No paper copies accepted. Late submissions are rejected automatically by the system. Upload early. § 2.4
Wed Apr 1
Apparent low bidder notified. Subject to bid review, references check, and Township Board approval. § 10.1
Fri Apr 17
Notice of award + Notice to Proceed, contingent on executed contract, bonds, and insurance certificates received within 10 days of award notice. § 10.2
Award basis

How they're scoring this

This is a low-bid solicitation, not best-value. Price wins, but only among responsive and responsible bidders.

The Township awards to the lowest responsible bidder whose bid is responsive to the bid documents. "Responsible" and "responsive" are separate hurdles. Either one can disqualify you regardless of price.
  1. Responsive bid (pass/fail). Your submission includes everything required, signed and notarized correctly, on the right forms, with no unauthorized changes to the bid documents. The Submission Checklist above is the responsiveness test.
    Lever: don't lose on a paperwork miss. Run the checklist back-to-front before upload.
  2. Responsible bidder (pass/fail). Per § 3, the Township evaluates bonding capacity, prequalification status, project history (three similar projects in five years), key personnel, and financial standing. The Township can reject a low bid for being non-responsible.
    Lever: front-load your qualifications statement. Don't bury the relevant projects. Township engineer will read this first if your price is in striking distance.
  3. Total bid price. Sum of all unit prices × quantities, plus any lump-sum items. No alternates on this project. Mathematically lowest bid that clears the responsive/responsible bar wins.
    Lever: get your unit prices right on the high-volume items like pipe, fittings, restoration. A 10% miss on a $400K line is a $40K miss on the bid.
  4. Reserved right to reject. Per § 10.3, the Township reserves the right to reject any or all bids and to waive informalities. Standard language. In practice, the Township engineer's recommendation drives the award decision.
    Lever: be the bid the engineer wants to recommend. Clean package, credible qualifications, no red flags on the corridor walk.
Bid package contents

What goes in the bid

PennBid upload, single PDF preferred. Order doesn't matter to the system, but it matters to the engineer reading it.

  1. Bid form, signed and dated by an authorized signatory. Use the form in Appendix A. § 2.5, App. A
  2. Unit price bid schedule, complete with no blanks. Total bid amount carried forward to bid form. § 2.6
  3. Bid bond at 10% of total bid amount. AIA A310 or equivalent. Treasury-listed surety licensed in PA. § 4.2
  4. Non-collusion affidavit, signed and notarized. Form in Appendix B. § 5.1, App. B
  5. PA Public Works Employment Verification (Act 127). E-Verify enrollment statement. Form in Appendix C. § 5.2, App. C
  6. Steel Products Procurement Act statement (Act 3 of 1978). Form D. § 5.3, App. D
  1. Bidder qualifications statement with three similar projects, owner contacts, and key personnel resumes. § 3.2, 3.4
  2. MBE/WBE participation plan naming subcontractor commitments and good-faith effort documentation if goals are not met. § 5.6
  3. Insurance certificates naming Township as additional insured with primary/non-contributory language. Pollution liability separate. § 4.5
  4. Proposed construction schedule showing substantial completion within 180 calendar days of NTP. § 9.1, 9.2
  5. Signed and acknowledged addenda receipt for each addendum issued. § 2.3
Internal

What you still need before anyone starts pricing

Things the bid requires that aren't in the documents themselves. Track these down before estimating starts.

  • Confirm bonding capacity for $3.8M single project. Call your surety. If they can't sit on $7.6M aggregate, line up a co-surety now, not in week three of pricing.
  • Verify your prequalification status. PennDOT prequal in water/sewer (work code 0530 or 0540) OR current Township vendor approval. Don't assume; pull the certificate or call the Township.
  • Identify MBE/WBE subs you'll commit to. 12% MBE + 7% WBE goals. Have firm names, certifications, and dollar values lined up before bid week, not after.
  • Walk the corridor before the pre-bid meeting on Feb 25. Look at the road condition, driveway counts, tree canopy, traffic patterns. The site walk is at the meeting but you want your own first.
  • Get the geotech report if not included in the bid package. Existing utility congestion in this corridor is on the as-built drawings, but soil conditions drive your trench and dewatering pricing.
  • Pull recent PA prevailing wage rates for Bucks County. The wage determination posted in the bid package controls, but cross-check against the latest L&I posting before pricing labor.
Clarifications

Questions to send before March 2

Submit through the PennBid Q&A portal. Township engineer's answers will be posted in the final addendum on or before March 6. Review and prioritize before sending.

  1. Section 3.1 states that bidders must be either PennDOT-prequalified or hold Township vendor approval. Please confirm whether PennDOT prequal under work code 0540 (sewer and water lines) is treated as equivalent to work code 0530 (water lines only) for the purposes of this solicitation.
  2. Section 6.4 requires continuous water service to residents during construction. Please clarify the maximum acceptable duration for a planned service interruption (after notice) for individual service connection transfers.
  3. Section 4.5.3 requires pollution liability coverage. Please confirm the location of the "former gas station parcel" referenced in the section, and whether any prior Phase I or Phase II environmental site assessments are available to bidders.
  1. Section 7.2 references the PA Prevailing Wage Act. The bid package includes a wage determination dated three months ago. Please confirm whether the Township will issue an updated determination if the L&I posting changes between bid date and award.
  2. Section 9.1 sets substantial completion at 180 calendar days from NTP. Given the seasonal restoration requirements in § 6.7 (final paving cannot be placed below 50°F), please confirm how a fall NTP would affect the substantial completion calculation and LD assessment.
  3. Section 5.6 establishes MBE/WBE participation goals of 12% and 7%. Please confirm whether MBE-certified suppliers (material providers) count toward the participation goal in addition to MBE-certified subcontractors performing on-site labor.